Signalization

New signalized interchanges are identified through TCIP improvements.
  • SH 317 at FM 2483 and Prairie View Road 
    • THE TWO INTERSECTIONS ON SH 317 WILL BE RELOCATED TOGETHER INTO ONE SIGNALIZED HIGHWAY INTERSECTION.
    • Status:
      • Under construction 
      • Completion expected in early 2019

IN PROGRESS:

  • Kegley Road at Adams Avenue
    • Adding pedestrian movements
    • Adding northbound and southbound left turns
    • Completion expected late 2018
  • Kegley Road at Airport Rd
    • New signal
    • Completion expected end of 2018
  • Greenview Drive at Adams Avenue
    • New signal
    • Completion expected end of 2018

Signals In Progress

Signalization In Progress - Kegley and Greenview

COMPLETED:

  • S. 1st Street at Avenue R
    • Installed new signal
  • S. 5th Street at FM 93
    • Installed new signal
  • Airport Road at Outer Loop (Research Parkway)
    • Installed new signal
  • S. Pea Ridge Road at Adams Avenue
    • Upgraded pedestrian signal & crossing
  • W. Adams Avenue (FM 2305) at Westfield Boulevard
    • Installed new signal

S 5th Street at FM 93

  1. 1
  2. 2
  3. 3

S. Pea Ridge Rd at Adams Ave

  1. 1
  2. 2

S 1st Street at Avenue R

  1. 1
  2. 2
  3. 3
  4. 4

Airport at Outer Loop (Research Pkwy)

  1. 1
  2. 2

W. Adams Ave at (FM 2305) Westfield Blvd

  1. 1
  2. 2

Completed Signals - West Temple

Signalization Complete - West Temple

Completed Signals - South Temple

Signalization Complete - South Temple